Validation Problem for Non-currency Resource Validity from Relative to No End Date

(Doc ID 2327226.1)

Last updated on NOVEMBER 20, 2017

Applies to:

Oracle Communications Pricing Design Center - Version 11.1.0.0.0 and later
Information in this document applies to any platform.

Symptoms

On : PDC 11.1.0.10.0 version, User Interface (GUI)

ACTUAL BEHAVIOR
-----------------------
There is no validation when setting non-currency resource validity to start as "Relative to Event Occurrence” + “From Start Of Billing Cycle” and validity to end as "No End Date".


EXPECTED BEHAVIOR
-----------------------
There should be validation to stop user to avoid this invalid configuration.


STEPS
-----------------------

1. Create a rule for a discount charge
2. Click open 'Amount Is Valid' dialog
3. Select "Relative to Event Occurrence" in 1 “From Start Of Billing Cycle”
4. Select "No End Date"
5. Click on OK to close 'Amount Is Valid' dialog
6. Click on Validate button from Discount Offer window


Note :

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms