Error: "Remaining Finish can't be earlier than Remaining Start," When Adding A New Activity in the Standard View.

(Doc ID 2328385.1)

Last updated on DECEMBER 01, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 17.9.0.0 and later
Information in this document applies to any platform.

Symptoms

Adding A New Activity in the Standard View With Default Duration 0 Fails, (Application Setting, General, set Default Duration for new activity is '0').


It is throwing Error as "Remaining Finish can't be earlier than Remaining Start".

For this new Activity, Remaining Early Finish Date will be 1 hour behind Remaining Early Start Date.

For example, Remaining Finish will be 09-Aug-17 23:00, where Start(Remaining Start) is 10-Aug-17 00:00


STEPS TO REPRODUCE:
1. Login P6 Web, Application Setting, General, set Default Duration for new activity is '0'.
2. Add A New Activity With Default Duration 0 will fail with error.

ERROR
-----------------------
"Remaining Finish can't be earlier than Remaining Start".


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot add new Activity with 0 duration.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms