Existing Supply is getting Rescheduled and Not Cancelled

(Doc ID 2328487.1)

Last updated on NOVEMBER 14, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.6.2 and later
Information in this document applies to any platform.

Symptoms

On running an ASCP plan, it is seen that for a given item there exists demand which can fully be met by On Hand available for this item.

A past due Purchase Requisition (supply) is also present  for the item considered.

Since the demand for the item is fully met by the on hand, user expects the existing supply (Purchase Requisition) to be cancelled. 

However planning recommends rescheduling of the existing Purchase Requisition.

 

Cause