Symptoms

ACTUAL BEHAVIOR
---------------
Resource Assignment CBS (Unifier WBS) are lost after create baseline.

EXPECTED BEHAVIOR
-----------------------
Resource Assignment CBS (Unifier WBS) should be kept after create baseline.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Push P6 WBS to Unifier WBS.
  2. Pull Unifier WBS to P6.
  3. Assign CBS to P6 Resource Assignments.
  4. Perform baseline, then the CBS ids assigned in step 3. is lost.


BUSINESS IMPACT
-----------------------
The issue has the following business impact: Due to this issue, users cannot CBS assigned got lost after create baseline

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms