Project Publication Of A Large Project Takes Hours

(Doc ID 2333121.1)

Last updated on DECEMBER 04, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.2.0.0 and later
Information in this document applies to any platform.

Symptoms

A single project containing over 100,000 activities can take anywhere from 1-4 hrs to publish to the extended tables.


Changes

 

Cause