ASCP Plan Not Calculating Component And Resource Requirements For 1 Of The Orgs - Was Working OK, Just Stopped Working

(Doc ID 2335892.1)

Last updated on DECEMBER 05, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

On Any Release

PROBLEM
-------------
3 Orgs in plan
1 org ABC - does not get planned orders for components and no resource requirements calculated
2 other orgs are fine.
Calendar is end date of 2051

This has been working fine for many months and just started failing.
We can see resource availability is calculated for the collected data and plan output

STEPS
--------
Unconstrained plan
90 days / 12 wks / 6 periods
no PTF or DTF checked.
Sales order demand only - no forecast


Cause