Unable To Update Activity ID In Details Window After Adding New Activity

(Doc ID 2337381.1)

Last updated on DECEMBER 22, 2017

Applies to:

Primavera P6 Professional Project Management - Version 15.1.6.0 to 15.1.6.0 [Release 15.1]
Primavera P6 Enterprise Project Portfolio Management - Version 15.1.6.0 to 15.1.6.0 [Release 15.1]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.1.6.0 to 15.1.6.0 [Release 15.1]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

After adding a new activity, when trying to modify the activity id on a different activity (that has a relationship) using the "Go To" link, the activity id is not editable

EXPECTED BEHAVIOR

Should be able to modify the activity id

STEPS

The issue can be reproduced at will with the following steps:

  1. Create 2 or 3 activities
  2. Add a relationship (predecessor or successor) to one of the activities
  3. Click on the Relationships tab in the Details section
  4. Create new activity and enter a name
  5. Highlight the activity with the relationship
  6. Click on the "GoTo" icon in the Relationships tab
  7. In the Relationships tab, move the cursor to the Activity box
  8. Observe the activity id is not editable
  9. Click on the Name box
  10. Click back on the Activity box
  11. Observe the activity id is editable
      


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms