Unable To Update Activity ID In Details Window After Adding New Activity
(Doc ID 2337381.1)
Last updated on JUNE 04, 2019
Applies to:
Primavera P6 Professional Project Management - Version 15.1.6.0 to 15.1.6.0 [Release 15.1]Primavera P6 Enterprise Project Portfolio Management - Version 15.1.6.0 to 15.1.6.0 [Release 15.1]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.1.6.0 to 15.1.6.0 [Release 15.1]
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
After adding a new activity, when trying to modify the activity id on a different activity (that has a relationship) using the "Go To" link, the activity id is not editable
EXPECTED BEHAVIOR
Should be able to modify the activity id
STEPS
The issue can be reproduced at will with the following steps:
- Create 2 or 3 activities
- Add a relationship (predecessor or successor) to one of the activities
- Click on the Relationships tab in the Details section
- Create new activity and enter a name
- Highlight the activity with the relationship
- Click on the "GoTo" icon in the Relationships tab
- In the Relationships tab, move the cursor to the Activity box
- Observe the activity id is not editable
- Click on the Name box
- Click back on the Activity box
- Observe the activity id is editable
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |