Resource Requirement Is Missing For Past Due Firm Orders

(Doc ID 2343916.1)

Last updated on JANUARY 22, 2018

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4.1 version, Memory Based Planner

ACTUAL BEHAVIOR
---------------
Resource requirement is missing for past due firm orders

Constrained without detailed Scheduling -

We ran the plan setting above plan options and checked the resource requirement for past due firm order but its missing.
Same we checked for the Future date and resource requirement is available for such firm work orders.


EXPECTED BEHAVIOR
-----------------------
Resource requirements should be available for past due firm work orders

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run ASCP Plan

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms