Can Individual Line Items on a Timesheet Be Approved or Rejected in Primavera P6 Web?

(Doc ID 2344643.1)

Last updated on JANUARY 16, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.1.5.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.5.0 and later
Information in this document applies to any platform.

Goal

Is it possible to approve only selected Activities in a Timesheet and not the entire Timesheet, and if so, how?
 

Solution