My Oracle Support Banner

When Synchronizing P6 Data to EBS Using Primavera Gateway the Error "The Task's Finish Date Must Be Earlier Than the Finish Date of the Parent Task" Occurs (Doc ID 2347628.1)

Last updated on JANUARY 11, 2018

Applies to:

Primavera Gateway - Version 16.1.0.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to synchronize data from P6 to EBS, the following error occurs.

ERROR
-----------------------
The task's Finish Date must be earlier than the Finish Date of the parent task.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References