When Importing a Project XML File Milestone Activities with a PrimaryResourceObjectid Are Not Assigned a Primary Resource. Activities that have the type Task are updated with a Primary Resource.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. In P6 Web create a project with 3 Activities. 1 Task, 1 Start Milestone, 1 Finish Milestone
2. Add the column Primary Resource to the Activities view (see screenshot)
3. Assign a Primary Resource to all 3 activities
4. Export the project as XML
5. Check the XML for the value PrimaryResourceObjectId. See that all 3 activities have a value assigned
6. Import the project as a new project
7. The Task activity will have the Primary Resource assigned, but the Start and Finish milestones will not

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms