Primavera Gateway P6 to Ebs Synchronization Is Failing with the Error "The Specified Planning Resource Is Not Enabled"

(Doc ID 2348993.1)

Last updated on JANUARY 15, 2018

Applies to:

Primavera Gateway - Version 16.1.0.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to synchronize project data from P6 to EBS, the following error occurs.

ERROR
-----------------------
The specified planning resource is not enabled.

Changes

 

Cause

Sign In with your My Oracle Support account