OPM Resource Requirements For Same Resource In Back To Back Operations Are Scheduled Days/Weeks Apart

(Doc ID 2352072.1)

Last updated on JANUARY 23, 2018

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.5 version, Constrained planning in All instances

Users are on 12.2.5 and have applied patch 22493520 Mandatory 12.2.5 VCP Consolidated Patch 2 for R12.SCP_PF.C.Delta.6 - They have MBP version MSONWL64.ppc 120.15.12020000.42.1220500.76 from one off patch 26694720 which is cum patch 12 on 12.2.5. They are running an ECC Classic Constrained Plan but are not enabling sequence dependent setups. However they do have Setup and Run time for the same resource in their OPM routings. The problem they're running into are large gaps between the setup and run operation for the same resource. Example data

Item = 29174188
Org = EME:700

There's a planned order qty = 360 with
Sugg Start Date = 08-FEB-2018
Sugg Due Date = 22-FEB-2018
Trans id = 187983623

Res Reqts
========
Dept = 700 - Res = SHE581- step 10 - Res hours = 0.7 - Start Date = 08-FEB-2018 - End Date = 08-FEB-2018
Dept = 700 - Res = SHE581- step 20 - Res hours = 0.606667 - Start Date = 22-FEB-2018 - End Date = 22-FEB-2018

The issue is why such a big 14 day gap between the two operations


EBS Source OPM process routing Routing for Product: 29174188 at Org: 700 Routing = SHE_581_FIL_SF_2.37
Valid from 01-JAN-2016 and up
Qty = 599.98800 Each
Step 10 - Oper = SHE_SET_581_0.7 - Step qty = 599.98800 Each
Step 20 - Oper = SHE_FIL_581_1.67 - Step qty = 599.98800 Each

step 20 has a step dependency setup as follows:

Previous step = 20
Operation = SHE_SET_581_0.7
Dependency Type = Finish-to-Start

The activities are setup as follows

Activity = SET shows Throughput
Res = SHE581 Proc Qty = 1440.02304 Useage = 0.7 HR
Res = SHEDL Proc Qty = 1440.02304 Useage = 0.7 HR

Activity = FIL shows Throughput
Res = SHE581 Proc Qty = 599.98800 Useage = 1.0 HR

Horizontal Resource Plan for
Resource = SHE581
Org = 700
Shows the resource is at 100% capacity from the beginning of Feb 2018 out to 26-FEB-2018

Res = SHEDL Proc Qty = 599.98800 Useage = 1.0 HR

They've been trying to set profile MSO: Additional Demand Slices for Shared Supply Rescheduling =-1 and 40 and sometimes it helps and sometimes not

EXPECTED BEHAVIOR
-----------------------
Expect the operations to be performed one right after the other instead of many days gap between the resources

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Setup Step depenedencies in OPM
2. Run collections and ASCP ECC Classic Constrained plan
3. Review resource planning and see many days gaps between resource operations for the same resource



Cause

Sign In with your My Oracle Support account