Realtime Load Plans Show A Running State But Date In The "Last Failed Time" Column Causing It To Appear As If The Load Plan Is Not Actually Running

(Doc ID 2355651.1)

Last updated on FEBRUARY 06, 2018

Applies to:

Primavera Analytics - Version 17.12.1.0 and later
Primavera Analytics Cloud Service - Version 17.12.1.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
-----------------------
The LOAD_PLAN_ON_DEMAND & LOAD_PLAN_REALTIME_PROJECT are showing:

This makes it appears that the load plans which have a "Last Failed Time" are not actually running.

EXPECTED BEHAVIOR
-------------------------
The LOAD_PLAN_ON_DEMAND & LOAD_PLAN_REALTIME_PROJECT should be running properly.

STEPS TO REPRODUCE
----------------------------
The issue can be reproduced at will with the following steps:

  1. Login to the Analytics Administration Application
  2. Browse to the P6 datasource (startel1) > Status
  3. Observe the status of the real-time load plans.

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms