EBS: PS: Unit of Effort Flag On - Causing Gaps in PS Plan (Doc ID 2357329.1)

Last updated on FEBRUARY 05, 2018

Applies to:

Oracle Production Scheduling - Version 12.2.6 and later
Information in this document applies to any platform.

Symptoms

This issue is causing Gaps in the PS Plan when "unit of effort" flag is on.

Regarding the "unit of effort" flag, even with our fix for the gap issue, we recommend user to investigate the two work orders "22936" and "22951" with
produced primary item quantity being "1.11" if these are data issue.

Workaround:
Investigating this issue development found that two work orders "22936" and "22951" with produced primary item quantity being "1.11" which is causing the
gap issue.

However, for now and since a majority of the work orders are producing quantity with 1. We are recommending that you should select "Schedule work
orders according unit of effort" (on Solver option page | General Tab in PS, but they should be able to set it on EBS) to No.
This will resolve your issue and also lead to some performance improvement as well.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.