Primavera P6 History Subject Area Does Not Show Data for the Fields Planned Duration, Actual Duration, At Completion Duration, Schedule % Complete, Performance % Complete

(Doc ID 2364736.1)

Last updated on FEBRUARY 22, 2018

Applies to:

Primavera Analytics - Version 17.7 and later
Information in this document applies to any platform.

Symptoms

In Primavera P6 Analytics the Project History Subject Area does not show data for some values that appear in the STAR database. Some of the fields are Planned Duration, Actual Duration, At Completion Duration, Schedule % Complete, Performance % Complete.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run the following query against the STAR database:
  select project_id, project_name, planned_duration, actual_duration, at_completion_duration, schedule_percent_complete, performance_percent_complete
  from w_project_d
  where datasource_id =2
  order by project_id
2. The query returns data for each project for all the fields
3. Create an analysis in OBIEE using the Project History subject area
4. Add the fields Planned Duration, Actual Duration, At Completion Duration, Schedule % Complete, Performance % Complete
5. Notice the fields have values for some projects but most fields are empty

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms