Activity Shows Baseline (BL)l Project Start / Finish Dates, Although BL Has 0 Activities. (Doc ID 2368263.1)

Last updated on FEBRUARY 03, 2019

Applies to:

Primavera P6 Professional Project Management - Version 8.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Activity shows BL Project Start / Finish dates, although the Project Baseline has 0 Activities.

EXPECTED BEHAVIOR
-----------------------
It should show blank BL Project Start / Finish dates.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a Project and create an Activity for it.
2. Create a Baseline based on the current Project, assign it as Project BL.
3. Delete the Activity, Update Baseline by checking the option "Delete from Baseline ...".
4. Create a new Activity with the same Activity ID as that which was created at step 1. Press F5 to refresh.
5. Notice that the new Activity shows "BL Project Start / Finish" dates.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot view correct Activity dates.



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.