Milestone Durations In Unifier Is Shown As 1 Day

(Doc ID 2369077.1)

Last updated on MARCH 16, 2018

Applies to:

Primavera Unifier Cloud Service - Version 17.11.0.0 and later
Primavera Unifier - Version 17.11.0.0 and later
Information in this document applies to any platform.

Symptoms

On : Unifier 17.11.0.0 version, Unifier Integration

ACTUAL BEHAVIOR
---------------

When syncing data from P6 to Unifier, milestones changing the 0 duration to 1 and the schedule dates are pushed further.
  

EXPECTED BEHAVIOR
-----------------------
Milestones duration should be 0 and the schedule dates should not be pushed further.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login P6 EPPM, open project
2. Run Send to Schedule Sheet, check Milestone activity duration in P6, it is 0
3. Check schedule sheet in Unifier, the Milestone activity duration is 1

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot view correct data in Unifier.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms