Enhancement Request - Timesheet Option Update Date Warn Users There Are Actuals Approved Before or After the Date They Are Changing

(Doc ID 2377257.1)

Last updated on APRIL 10, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 17.7 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 17.1 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

---------------

There is no notification using the Update Dates feature, that there are Actuals logged before the new start or after the new finish of the Activity. 

 

EXPECTED BEHAVIOR

---------------

When you change the start date of an Activity that has logged hours. you should be notified that there are Actuals outside the new dates. 

 

STEPS TO REPLICATE

---------------

  1. Log hours in a Timesheet for a specific Activity.
  2. Approve the Timesheet.
  3. Use the Update Dates feature in Team Member to move the start date of the Activity past the days that have logged hours.
  4. There is no warning to alert you that Actuals are present.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms