EBS: PS: Adding Time Event Causes Jobs To Schedule Through Weekend

(Doc ID 2382553.1)

Last updated on APRIL 04, 2018

Applies to:

Oracle Production Scheduling - Version 12.2.6 and later
Information in this document applies to any platform.

Symptoms

Issue:
Adding Time Event Causes Jobs to Schedule Through Weekend

After adding a time event on a resource in a PS model and repairing that
resource is will schedule jobs through the entire weekend even thought there is delay time there.
The xml containing the exported scenario for this model, the dxt file saved by the scheduler post solve. This is not able to duplicate this issue in the
xml file but can in the FA-17-BAY3 (already solved) scenario in the dxt file.

Why does it Scheduling jobs through the Delayed time with the dxt Model ?

Cause

Sign In with your My Oracle Support account