Error "0.00h is an Invalid Unit of Measure" Displays When Adding a Material Assignment and Navigating to Resource Assignments in P6 Professional.

(Doc ID 2386158.1)

Last updated on APRIL 19, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.14.0 to 15.2.17.0 [Release 15.2]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.14.0 to 15.2.17.0 [Release 15.2]
Primavera P6 Professional Project Management - Version 15.2.14.0 to 15.2.17.0 [Release 15.2]
Information in this document applies to any platform.

Symptoms

If a Material Resource with non-time Unit of Measure (e.g., Cubic Yards / CY) is added to a Project and when selecting the Resource Assignments page an error will display "0.00h is an invalid Unit of Measure" even when a valid, existing Price/Unit Filter is already applied.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Select any Project with Labor Resource Assignments.
  2. Next, select the Resource Assignments View
  3. Add a Filter criteria with Price/Unit equals (=) $1.00/hr. Save.
  4. Result: New Filter works and throws no error.
  5. Next, add a Material Resource Assignment to any Task (e.g., non-time Unit of Measure like Cubic Yards/CY).
  6. Result: repeating error message "0.00h is an invalid Unit of Measure." for every Material Assignment in the View.

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms