Financial Period Calendar Shows 11 August Both Saturday And Sunday
Last updated on APRIL 16, 2018
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 17.12.0.0 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
Financial Period calendar shows 11 August Saturday and Sunday
EXPECTED BEHAVIOR
-----------------------
Financial Period Calendar should not show duplicate date on 2 days
BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot create financial periods using the repeating dates as end dates.