My Oracle Support Banner

Planned Order With Compression Days (Doc ID 2388855.1)

Last updated on MAY 16, 2018

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms


PROBLEM
-------------
There are several Planned orders in BA3 with compression days but in my eyes we don't need to buy that much material (1020170, 1020171, 1020172).

Example ítem 1020170. We have planned order quantity in total 7200, with this we have material to cover demand until july.

STEPS
--------
Launch EDD plan.


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.