When Sending Initial Planning Baseline From P6 To Unifier Through Gateway, Planned Units are Doubled

(Doc ID 2394848.1)

Last updated on MAY 07, 2018

Applies to:

Primavera Gateway - Version 15.1.0.0 to 15.1.6.0 [Release 15.1]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
----------------------
When sending Initial Planning baseline from P6 to Unifier through Gateway, double units are processed. For example:

1. On P6, the Planned Units of one activity is {value} in a project. Note: this project has a baseline with the same activity and same Planned Units field value.
2. Run Gateway synchronization to send the Activity data from P6 to Unifier.
2. On Unifier, check Schedule Manager > P6 Summary Sheets (Type: Initial Planning Baseline), notice that the Planned Units field value is doubled (i.e. {value} * 2).

EXPECTED BEHAVIOR
-----------------------
The Planned Units field value of the P6 project activity is synchronized to the Unifier project activity correctly.

BUSINESS IMPACT
-----------------------
The issue has the following business impact: Due to this issue, users cannot see the correct Planned Unit in Unifier.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms