Enhancement Request: Is It Possible To Filter Activities Based On Predecessor Activity Status?
(Doc ID 2395080.1)
Last updated on MAY 06, 2020
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 16.2.0.0 and laterPrimavera P6 Professional Project Management - Version 16.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.2.0.0 and later
Information in this document applies to any platform.
Goal
Is it possible to setup an activity level filter in P6 Pro Client to show activities that have predecessors with "Completed" activity status?
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |
References |