ASCP Planned Orders Not Respective Supplier Calendar For Weekly And Monthly Buckets

(Doc ID 2396699.1)

Last updated on MAY 09, 2018

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms


Customer has one year horizon with 60 days daily, 24 weeks weekly and rest of
them monthly buckets. For the planned orders for purchasing, have
Sugg Dock Date correctly suggested based on supplier calendar.
However, for weekly and monthly buckets it is not respecting supplier calendar.

This issue is happening for all items and all time for both weekly and
monthly. However, this issue is not happening for daily buckets.

Cannot have whole planning horizon to daily buckets as it would affect
system performance and ASCP runs for significantly huge time

This was never working. The only thing that it is working for is daily
buckets.

Need to get this functionality working for Weekly and Monthly buckets

When increasing the number of daily buckets, the plan is taking incredibly
long time to run which is not acceptable.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms