How The Forecast Quantity With Project/seiban Reference Is Consumed?

(Doc ID 2396756.1)

Last updated on MAY 16, 2018

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.7 and later
Information in this document applies to any platform.

Goal

Forecast is defined as below:

Item: AXXX
Quantity: 1000
Project Number; SEIBAN-001

SO:1001 is entered and booked as below:

Item: AXXX
Quantity: 10
Project Number: SEIBAN-001

SO:1002 is entered and booked as below:

Item: AXXX
Quantity: 50
Project Number: SEIBAN-002

SO:1003 is entered and booked as below:

Item: AXXX
Quantity: 100
Project Number: null

We would like to know how the the forecast will be consumed by ASCP? Can we set the system to consume the forecast only by SO: 1001, since they have identical Project number reference.
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms