Update to Expected Finish Date via Update Dates Feature in Timesheets Shifts 1 Day Earlier.

(Doc ID 2401005.1)

Last updated on MAY 24, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 17.7 to 17.12.4.0 [Release 17.7 to 17.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 17.7 to 17.12.4.0 [Release 17.7 to 17.12]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Date update submitted via "Timesheet -> Update Dates" shifts 1 day earlier (e.g., Apr-24 becomes Apr-23).

EXPECTED BEHAVIOR
-----------------------
Date update submitted via "Timesheet -> Update Dates" should not change.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Login to P6 Web, configure a Project to use Team Member with Status Update Review enabled.
  2. Login to P6 Team Member Web, navigate to Timesheets page, click "Update Dates", input date for "Expected Finish" and save it.
  3. Login to P6 Web, notice that the "Expected Finish" column has been updated with a date 1 day earlier than submitted.


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot submit correct dates via "Timesheet -> Update Dates".

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms