When Updating the Activity % Complete in Team Member, the Remaining Duration Changes to Zero

(Doc ID 2407318.1)

Last updated on JUNE 07, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 17.12.2.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 17.12.2.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When entering the % complete in Team Member, the Remaining Duration goes to zero.

EXPECTED BEHAVIOR
-----------------------
Expect Remaining Duration to not go to zero.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Set up a project for Team Member updates by owner, with assignments to the owner ID.
  2. Log into Team Member with the owner ID.
  3. Enter Actual Start and enter a % complete value. Notice the remaining duration goes to zero.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms