When Synchronizing a Project in Primavera Gateway the Warning "Summarize Project Not Completed Within 300 seconds. Increase Wait Time in Gateway Settings or Summarize the Project Within P6" Occurs
(Doc ID 2407647.1)
Last updated on AUGUST 20, 2019
Applies to:
Primavera Gateway - Version 16.1.0.0 and laterPrimavera P6 Enterprise Project Portfolio Management - Version 16.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.0.0 and later
Information in this document applies to any platform.
Symptoms
When attempting to synchronize project data from P6 using Primavera Gateway, the following error occurs.
ERROR
-----------------------
Warning Found in Load from Source
Failure Details:
Summarize project not completed within 300 seconds. Increase wait time in Gateway Settings or summarize the project within P6
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a new Project Data business flow or edit an existing business Project Data business flow
2. Enable the option Summarize project(s) before synchronization? on the Source App Parameters screen
3. Run the synchronization and it will complete successfully but there will be a warning in the Load from Source step
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |