When Synchronizing a Project in Primavera Gateway the Warning "Summarize Project Not Completed Within 300 seconds. Increase Wait Time in Gateway Settings or Summarize the Project Within P6" Occurs

(Doc ID 2407647.1)

Last updated on JUNE 05, 2018

Applies to:

Primavera Gateway - Version 16.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 16.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.0.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to synchronize project data from P6 using Primavera Gateway, the following error occurs.

ERROR
-----------------------
Warning Found in Load from Source

Failure Details:
Summarize project not completed within 300 seconds. Increase wait time in Gateway Settings or summarize the project within P6

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a new Project Data business flow or edit an existing business Project Data business flow
2. Enable the option Summarize project(s) before synchronization? on the Source App Parameters screen
3. Run the synchronization and it will complete successfully but there will be a warning in the Load from Source step

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms