Negative Value Appears as Zero in Summary Spread Data

(Doc ID 2409994.1)

Last updated on JUNE 18, 2018

Applies to:

Primavera P6 Professional Project Management - Version 15.2.0.0 to 15.2.17.0 [Release 15.2]
Information in this document applies to any platform.

Symptoms

Summary data displays negative numbers as zeros in Primavera P6 Professional and PPM API 15.2. When the same data is displayed in EPPM, the negative values are shown correctly.

Steps to reproduce:

1. Create a new project (NG New).
2. Add an activity.
3. Add a resource to the activity.
4. Set the resource's "Budgeted Cost" to a negative value.
5. In the API code, add the following lines:

Cost XFY = sp.getBaselinePlannedTotalCost();
Cost PC = sp.getPlannedTotalCost();

6. Summarize the project.
7. Run the API code.

- In EPPM, negative value are displayed correctly.
- In PPM/API, negative values are displayed as zeros.



Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms