DRP Plan Generating Projected Stock Out Exception For Items Having Sufficient Supply Arriving The Same Day

(Doc ID 2413450.1)

Last updated on JUNE 20, 2018

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.6.2 and later
Information in this document applies to any platform.

Goal

Qn1:We are seeing, few cases, where DRP plan is generating 'Items with Projected Stockout' even if we have sufficient supply from Day1.

Attaching a document containing screenshots for the same.

Plan run on 07-JUN
Demand is past due from 06-JUN - 23:59
Purchase order supply due 07-JUN 08:00
Stock out exception is based on supply coming on 07-JUN at 08:00 and has start date of 07-JUN 05:19 - so stock out is only valid for a couple of hours
 
Can we suppress the exception when it is given based on hourly data ??

The planners are using APCC to review these exceptions and are chasing a lot of "ghosts" due to how this issue.
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms