EBS: PS: Ideal Seq. Does Not Respect Dates - Prebuild+DRA+1Day Buckets Instead of CRO (Doc ID 2413888.1)

Last updated on JUNE 21, 2018

Applies to:

Oracle Production Scheduling - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

Question: In PS, is there a way that using Campaign Run Optimization that the requested dates are respected and will just sequence the work orders for the day?

Answer: Suggest they evaluate using DRA instead of CRO.

 

However, PS has a bug when you use solver option: Prebuild+DRA+1 day bucket instead of CRO.
The bug is related to Fixed Time Fence. If all resources have the same time fence then PS works as it should.
However,  If resources have different time fence, then PS doesn't work as it should and respect the dates.

Solver Options:
Scheduling Bucket := 1 day
Build Strategy := Prebuild
Prebuild Policy := Dynamic Resource Allocation
Enable Campaign Run Optimization := No

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.