Finish Milestone Date Changes After Milestone Creation in P6 Web. (Doc ID 2416299.1)

Last updated on JULY 30, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 17.7 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR:
--------------------
Milestone date does not save to the date updated, but changes to the day before when not showing time, or keeping the default of midnight set.

EXPECTED BEHAVIOR:
-------------------------
For date to stay as entered.

STEPS:
-------
The issue can be reproduced at will with the following steps:
1. Open Project. Make sure User Preference is set to not show time.
2. Select Finish Milestone Activity.
3. Change the Finish Date to some date in the Future.
5. Save the new Activity.

Result: The Finish Date changes to a day before the date selected..
Expected Result: The Finish Date is not changed on save.

BUSINESS IMPACT:
--------------------
The issue has the following business impact:
Due to this issue, users cannot enter the date on Activity correctly the first time.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.