Start Milestone Dates Are Disappearing After Schedule.

(Doc ID 2418995.1)

Last updated on JULY 09, 2018

Applies to:

Primavera P6 Professional Project Management - Version 15.2.14.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR  
---------------
Some Activity (Start Milestone) dates are disappearing after Scheduling.

EXPECTED BEHAVIOR
-----------------------
Date should not disappear while run a Schedule.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open Project.
2. Select Activity, mark 'Started' to 18--Apr-18.
3. Press F9 to Schedule.
4. Select Activity, uncheck 'Started'.
5. Press F9 to Schedule.
Note: Activity Started and Finished date will be null.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot see date for certain Activities.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms