When Synchronizing Data From P6 to Unifier the Error "P6 Summary Data Contains CBS Code Which Is Not a Leaf Node in Unifier Cost Sheet <CBS Code Value>" Occurs

(Doc ID 2422971.1)

Last updated on JULY 13, 2018

Applies to:

Primavera Unifier - Version 16.1.0.0 and later
Primavera Unifier Cloud Service - Version 16.1.0.0 and later
Primavera Gateway - Version 16.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 16.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.0.1 and later
Information in this document applies to any platform.

Symptoms

When running a P6 Summary Sheet integration from P6 to Unifier the following error occurs,

P6 Summary Data Contains CBS Code which is not a Leaf Node in Unifier Cost Sheet <CBS Code Value>

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Assign a top level CBS Code to an Activity, Resource Assignment or Expense in P6
2. Run the Send to Unifier synchronization to create the Summary Sheet
3. Check the logs in the Gateway Monitoring tab. Locate the error in the Update Destination step.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms