Symptoms

When attempting to Copy and Paste a project with an assigned Baseline in P6 the Baseline is no longer assigned to the newly created project.

STEPS TO REPRODUCE:

  1. Login to P6 Professional
  2. Open Project
  3. Assign Baseline to Project
  4. Perform Copy and Paste
  5. Open the Copied Project
  6. Observe that the newly created project, from the Copy and Paste process, no longer has the baseline assigned

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.