My Oracle Support Banner

WBS Summary Bar Does Not Show Correct Start and Finish Dates When Viewing in P6 Web. (Doc ID 2424112.1)

Last updated on JULY 17, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 16.2.12.0 to 16.2.14.0 [Release 16.2]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR:
----------------------
WBS Summary Bar in P6 Web gives wrong result. When we provide the Start and Finish dates of Activities, they get rolled up to WBS which is fine, but the WBS Summary Bar shows the wrong result as per roll-up dates of Activities. The dates are correct when using P6 Pro.

EXPECTED BEHAVIOR:
-------------------------
The WBS Summary Bar should show the Earliest ES and Latest EF of the Activities contained within.

STEPS:
-------
The issue can be reproduced at will with the following steps:
1. Open Project in P6 Professional.
2. The bars are correct.
3. Open the same Project in P6 Web.
4. Notice the Start date is using the System Date.

BUSINESS IMPACT:
---------------------
The issue has the following business impact:
Due to this issue, users cannot rely on dates for WBS Summary Bars when viewing in the Web.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.