Oracle Communications MetaSolv Solution - Version 6.2.0 and laterInformation in this document applies to any platform.
Symptoms
After supp cancelling an order with a pre-order prov plan, order is not marked closed when the last task is marked as not required.
Steps to re-create the problem
===========================
1. Create PSR order
2. Assign pre-order prov plan
3. supp cancel the order
4. Mark all the task as not required.
5. Order does not get closed even though there are no tasks open.
Changes
Cause