"Update" Button Not Active When Using Update Baseline (Doc ID 2444628.1)

Last updated on SEPTEMBER 26, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.1.0.0 and later
Primavera P6 Professional Project Management - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When trying to run Update Baseline with only "All Activities" marked, the 'Update' button is greyed out and can't be used.

EXPECTED BEHAVIOR

Able to update the baseline with only "All Activities" marked in the options.

STEPS

The issue can be reproduced at will with the following steps:

  1. Sign in to P6 Pro
  2. Open a project with a baseline to be updated
  3. Project > Maintain Baseline > Highlight the baseline and click "Update"
  4. Uncheck all check boxes. The only mark should be next to "All Activities"
  5. The "Update" button is greyed out and cannot be clicked.

Cause

To view full details, sign in with your My Oracle Support account.