Remaining Duration Changes For An Activity With % Complete Updated From Team Member. (Doc ID 2449876.1)

Last updated on SEPTEMBER 26, 2018

Applies to:

Primavera P6 Team Member - Version 17.12.4.0 to 17.12.7.0 [Release 17.12]
Information in this document applies to any platform.

Symptoms

Description:

Changing % complete in Team Member will change the Finish date. Performing the same action in P6 Professional does not have the same effect.

Steps:

1. In Team Member change the % Complete for an Activity set as Physical % complete and Fixed Duration & Units.
2. Save.
3. Notice the Finish date is changed.
4. In P6 Professional make the same change.
5. Notice the Finish date remains unchanged.
6. Change the value in Team Member to 100% causes the following error: Q63-INS-1050 : Error while trying to perform update: Errors located:RemainingDuration: Since the Duration Type is Fixed Duration & Units, setting Remaining Duration to 0 is not allowed.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.