P6 Summary Cost Values Do Not Equal the Sum of the Cost Values Underneath It (Doc ID 2458148.1)

Last updated on APRIL 05, 2021

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 4.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.3.2.0 and later
Information in this document applies to any platform.

Symptoms

 When looking at a Summary Cost Value, the Sum of the values underneath it do not equal the cost in the Summary Band

 

In the example above, we see there are 5 activities that have a budgeted cost shown of $136.45 and the Summary Band Cost = $818.68

If you add up the $136.45 we get a total of $818.70.  So it appears as the cost is off by 2 cents.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution

My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.