Goal

On : 12.1.3.9.2 version, Memory Based Planner in PROD

Users are running unconstrained Plan with Org WXI , SYD, IPH and DAL ..etc. They make semi conductors and use item level shrinkage for Make, Buy and Inter Org Demands. Planners are observing that Expected scrap calculation only happens for

1) Make

2) Buy Items

3) Does not occur Inter Organization Transfer Items.

Example : 1249927 has sourcing rule as : SYD org source the item from WXI org. SYD has shrinkage rate : 0.1 - APS data does not account shrinkage rate and no expected scrap is calculated for Planned Orders.

This looks to be the same as ER <bug 6998109>. Can it be confirmed this is an ER bug and that it's not going to be fixed/implemented anytime soon?
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.