Error: "AFMGS-2376-5" When Adding Risk Pessimistic Columns After A Risk Analysis Was Executed
(Doc ID 2460984.1)
Last updated on JUNE 04, 2019
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 18.8 to 18.8 [Release 18.8]Oracle Prime Cloud Service - Version 18.4 to 18.8 [Release 18.4 to 18.8]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.4 to 18.8 [Release 18.4 to 18.8]
Information in this document applies to any platform.
Symptoms
When attempting to display Risk Dates in P6 Client:
- Post response Activity Pessimistic Finish
- Post response Activity Pessimistic start
- Pre response Activity Pessimistic Finish
- Pre response Activity Pessimistic start
the following error occurs.
ERROR
Event Code: AFMGS-2376-5
Message: TCArcturusFormatMgr.GetStartDateFieldName: pre_pess_finish_date has no start date.
STEPS
The issue can be reproduced at will with the following steps:
- Create a project in P6, create 2 activities and give them each 10 days of duration
- Go into Gateway > Master Data > Send Resources to Prime Business Flow > Run it (Make sure to include Global Calendars and Resources Calendars)
- Go into Prime Projects and create a project with the same ID in P6
- Go back into Gateway > Project Data > Send P6 Project Data to Prime > Run it (This will bring over the activities from P6 into Prime)
- Go into Prime and Open the schedule App
- Go to Actions > Apply Activity Uncertainty (Accept Defaults)
- Add columns to view: Remaining Duration, Minimum Duration, Most likely Duration, Maximum Duration, Uncertainty Distribution
- Select Risks App > Go to Register
- Add a Risk
- Select Probability
- Pre- Response
- Shape = Single Point
- Most Likely = 80%
- Select 'Respond'
- Select Under Post Response
- Shape = Single Point
- Most Likely = 20%
- Select Schedule Impact
- Pre Response
- Shape = uniform
- Minimum = 30d
- Maximum = 50d
- Select 'Respond'
- Select Under Post Response
- Shape = uniform
- Minimum = 3d
- Maximum = 6d
- Pre Response
- Select 'Activity'
- Assign an activity to the Risk.
- Go back to Schedule and Schedule the project (May have to give the total float in settings a value if an error happens)
- Go to Risks > 'Run Analysis'
- Select dropdown in 'Response Context' = Pre and Post Response.
- Select 'Analyze'
- Go to Schedule App add the following columns, these should have dates now.
- Pre Response Pessimistic Start Date
- Pre Response Pessimistic Finish Date
- Post Response Pessimistic Start Date
- Post Response Pessimistic Finish Date
- Go back into Gateway > Project Data > Send Prime Project data to P6
- Set EPS location in Flow
- Go back into P6 and now these columns show have values.
- Pre Response Pessimistic Start Date
- Pre Response Pessimistic Finish Date
- Post Response Pessimistic Start Date
- Post Response Pessimistic Finish Date
- Log into P6 Client
- Open the project you created in Step 1
- Under the General Section add the following columns to your layout
- Post response Activity Pessimistic Finish
- Post response Activity Pessimistic start
- Pre response Activity Pessimistic Finish
- Pre response Activity Pessimistic start
- Error will show after adding all the columns
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |