Plan Orders of Dependent Demand Under the One Subassembly Are Not Generated in ASCP
(Doc ID 2464781.1)
Last updated on OCTOBER 16, 2019
Applies to:
Oracle Advanced Supply Chain Planning - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
On : 12.1.3 version, Memory Based Planner
ACTUAL BEHAVIOR
---------------
After run ASCP, plan orders of dependent demand under the one subassembly are not generated at all.
EXPECTED BEHAVIOR
-----------------------
After run ASCP, all dependent demand should be generated.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run ASCP
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |