Symptoms

ACTUAL BEHAVIOR
---------------
User can mark activity as Complete in Team Member but cannot enter time

EXPECTED BEHAVIOR
-----------------------
User should be able to mark as Complete and enter time

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Launch Team Member
2. Highlight activity
3. Click Checkbox to mark activity as Complete
4. Observe the time entry boxes are grayed out

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users are confused as to how to update activities and enter time

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.