WIP Order Completion Date Goes One Day Back When Released From ASCP Workbench (Doc ID 2474894.1)

Last updated on SEPTEMBER 11, 2019

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3.9.1 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.9.1

Issue :

when the planned orders are released from the ASCP Workbench for the unconstrained plan, the implement date is same as suggested due date, but when released and work orders are created, it goes one day back.

the profile MSC: Default Time Stamp for Make Planned Order Release to 23:59:59. After setting this profile when releasing a single planned order, the corresponding work order shows the correct date.

Issue occurs only multiple planned orders are released at the same time.

One more observation:

when all the planned orders are manually selected for release, the work order completion date is correct.

but all planned orders are selected ( tools > select all for release), issue occurs.

the issue is also strange. for first work order the date will be same but timestamp will be 00:00:00, and rest all work orders will be one day back with timestamp 23:59:00


 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.