ATO Model Not Exploding All BOM Levels Into The MDS (Doc ID 2487186.1)

Last updated on OCTOBER 19, 2019

Applies to:

Oracle Materials Requirement Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Master Demand Schedule in PROD

Users have an ATO model BOM like the one below that will only explode into a Master Demand Schedule (MDS) down to Level 1 item = JMLKLC-05 but will not go any further. As a result, all the level 2 and 3 items are not being planned in MRP

BOM
===
Level Item
0 JMLKLC
1 + JMLKLC-01
1 + JMLKLC-02
1 + JMLKLC-03
1 + JMLKLC-04
1 03M_JM_CM_ALL
1 12M_JM_CM_ALL
1 60M_JM_CM_ALL
1 120M_JM_CM_ALL
1 - JMLKLC-05
2 - JMLKLC-0501
3 + JMLKLC-ASSY
3 + JMLKLC-BLK
3 9165301
2 - JMLKLC-0502
3 + JMLKLC-ASSY
3 + JMLKLC-BLK-WOH
3 8078001
3 8813201
3 8351801
3 9165301

Other ATO models are similarly setup, however they explode down through all levels of the BOM as expected. Item = JMLKLC-05 is confirmed to be setup as a make item

EXPECTED BEHAVIOR
-----------------------
Expect all the BOM levels to explode and show in the MDS

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Explode forecast for ATO Model into an MDS
2. Review the model explosions and find most explode down through the entire BOM but one model does not

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution