P6 Web Services Is Not Loading the Correct Baseline Dates for Activities (Doc ID 2496431.1)

Last updated on FEBRUARY 09, 2021

Applies to:

Primavera Web Services - Version 17.12.3.0 to 17.12.10.0 [Release 17.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 17.12.3.0 to 17.12.10.0 [Release 17.12]
Information in this document applies to any platform.

Symptoms

Baseline Dates are not loading correctly using P6 Web Services ActivityService after upgrading from P6 8.4 to P6 17.12. The dates do not match the dates shown in P6 Professional.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open a project with at least two baselines assigned. The current project and the baselines should all have different Activity Start and Finish dates in order to demonstrate the issue.
2. Assign the baselines to the project. Assign one baseline as the Project baseline. Assign one baseline as the Primary baseline.
3. Create a SoapUI request to pull out the baseline dates: 
    <v1:ReadActivities>
        <v1:Field>Id</v1:Field>
        <v1:Field>Name</v1:Field>
        <v1:Field>StartDate</v1:Field>
        <v1:Field>FinishDate</v1:Field>
        <v1:Field>BaselineStartDate</v1:Field>
        <v1:Field>BaselineFinishDate</v1:Field>
        <v1:Field>Baseline1StartDate</v1:Field>
        <v1:Field>Baseline1FinishDate</v1:Field>
     </v1:ReadActivities>

  
4. See the baseline dates do not match what is appearing in P6.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!