My Oracle Support Banner

Resource Group Moves Two Levels When Importing New Resources. (Doc ID 2496743.1)

Last updated on MARCH 06, 2019

Applies to:

Primavera P6 Professional Project Management - Version 16.2.0.0 to 17.12.10.0 [Release 16.2 to 17.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.2.0.0 to 17.12.10.0 [Release 16.2 to 17.12]
Information in this document applies to any platform.

Symptoms

DESCRIPTION:

Resource Group moves two levels when Importing new Resources.

When using the Microsoft Project (MSP) XML Import and selecting a Resource Group (at say level 3 in the Resource Group hierarchy) in the Import Template, the Resources go into the selected Resource Group, but the Resource Group moves up to level 1. The Resource Group should stay at level 3.

EXPECTED BEHAVIOR:

The Resource should be Imported into proper level.

STEPS:

The issue can be reproduced at will with the following steps:
1. Import XML into P6.

BUSINESS IMPACT:

The issue has the following business impact:
Due to this issue, users cannot get the Resource under the proper level.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.